Decision Maker: Director of Resources (Ashley Hughes)
Decision status: Recommendations Approved
Is Key decision?: Yes
Is subject to call in?: No
That it be DETERMINED that of £0.497m of the Capital resource for Planned, Preventative Maintenance is allocated for essential works at Hyde Town Hall is approved.
Hyde Town Hall requires works totalling £0.497m to remove asbestos from the basement and to install 4 new boilers. A capital budget of £1.896m was approved at Executive Cabinet on 29 September 2021 for general use across the corporate estate for such works.
Publication date: 01/08/2024
Date of decision: 01/08/2024
Accompanying Documents: