25/02/2025 - Entering into a G-Cloud 14 Call-Off Contract ref: 2575    Recommendations Approved

To seek approval to enter into a G-Cloud 14 Call-Off Contract to continue using the HPA2 system for a further 3 years.
This system is necessary to meet the Council’s business needs and to meet the requirements of the Homelessness Reduction Act 2017.
The contract extension will cover 3 years, with a total contract value of £34,500

Decision Maker: Director of Place (Julian Jackson)

Decision published: 04/03/2025

Effective from: 05/03/2025

Decision:

That it be DETERMINED that:

Tameside Council enters into a G-Cloud 14 Call-Off Contract to continue using the HPA2 system for a further 3 years.


20/02/2025 - Duty To Consult Grant ref: 2576    Recommendations Approved

To accept the grant of £17,694

Decision Maker: Director of Place (Julian Jackson)

Decision published: 04/03/2025

Effective from: 28/02/2025

Decision:

That it be DETERMINED that:

1.       Tameside Council accepts £17,694 offered through the Nature for Climate Fund via the Department for Environment, Food & Rural Affairs.


25/02/2025 - Local Development Scheme Update ref: 2574    Recommendations Approved

To ensure the Council has an up to date Local Development Scheme as required by Section 15 of the Planning and Compulsory Purchase Act 2004 (as amended and meet the requests of the Deputy Prime Minister that all local planning authorities produce an updated Local Development Scheme (LDS) within 12 weeks of the publication of the NPPF, i.e. by no later than 6 March 2025.

Decision Maker: Director of Place (Julian Jackson)

Decision published: 04/03/2025

Effective from: 05/03/2025

Decision:

That it be DETERMINED to:

1.       Publish and bring into effect in accordance with the date of this decision the updated Local Development Scheme as presented at Appendix 1.


25/02/2025 - Enville House, 4 Richmond Street, Ashton-under-Lyne, OL6 7TX ref: 2573    Recommendations Approved

To seek approval to the surrender of the lease granted to The Guinness Partnership for Enville House and simultaneous grant of a new lease for the property to Ashton Pioneer Homes.

Decision Maker: Director of Place (Julian Jackson)

Decision published: 03/03/2025

Effective from: 05/03/2025

Decision:

That it be DETERMINED that:

1.     The Council accept the surrender of the leasehold interest in Enville House from The Guinness Partnership.

2.     Simultaneous to the surrender, the Council grants a new 125-year lease of Enville House to Ashton Pioneer Homes.


26/02/2025 - Demolition of Former Astoria Bingo Hall, Hyde ref: 2571    Recommendations Approved

Emergency demolition works under Section 78 of the Building Act 1984 are undertaken at the site of the Former Astoria Bingo Hall, Hyde.
That all fees and costs incurred as a consequence of the demolition works are placed as a Land Charge on the subject site.

Decision Maker: Director of Place (Julian Jackson)

Decision published: 28/02/2025

Effective from: 06/03/2025

Decision:

That it be AUTHORISED that:

1.       Emergency demolition works under Section 78 of the Building Act 1984 are undertaken at the site of the Former Astoria Bingo Hall, Hyde.

2.       That all fees and costs incurred as a consequence of the demolition works are placed as a Land Charge on the subject site.


24/02/2025 - St Anne’s Primary School - Reception Works ref: 2572    Recommendations Approved

Decision Maker: Executive Member (Lifelong Learning and Culture)

Decision published: 28/02/2025

Effective from: 04/03/2025

Decision:

That it be DETERMINED that:

1.       Approve that the remaining budget for St Anne’s Primary School for the construction of a new front entrance to the school is allocated to Victorious Academies Trust upon academisation.

2.       Approval to enter into a Grant Funding Agreement with St Anne’s Primary School to award the remaining budget for the construction a new front entrance to the school to the Trust to complete the works following academisation.